In recent years, the use of precast concrete elements has become more and more widespread

2022-11-17 00:00:00
times

The use of precast concrete components is becoming more and more widespread, but in order to extend its working efficiency and time, some measures are generally adopted in the proportion design.

Mixing Class I fly ash with the same color into the concrete will not only reduce air bubbles in the precast concrete components produced by the precast concrete component manufacturer, but also the "morphological effect" of the fly ash and the high-efficiency water-reducing agent can improve the fluidity of the mixture, making it easy for the concrete to evenly cover the entire formwork, and the surface will appear denser, giving people a delicate and touching texture.

Use a non-air-entraining water-reducing agent and compound a defoaming agent to reduce the air content of the mixture. An effective defoaming agent can not only burst the bubbles quickly, but also prevent the regeneration of bubbles for a long time.

Strictly control the water-cement ratio of concrete. On the premise of satisfying cement hydration and improving construction workability, the water-cement ratio should be reduced as much as possible to improve the compactness, durability and smoothness of concrete.

The construction technology and quality control points of complete sets of equipment for concrete precast component manufacturers are mainly divided into several aspects:

1. Combined steel mold.

According to the size of the hanging board, the steel formwork is combined and finalized on site to shape the formwork system. Strictly implement the construction specifications of the formwork project to ensure that the steel formwork and its supports have sufficient strength, stiffness and stability. The inside of the formwork should be flat, with tight joints and no leakage of slurry. After the formwork is installed, carefully check whether the formwork is placed flat. During the concrete pouring process, send someone to check the flatness of the formwork.


混凝土预制构件厂家


①Process flow.

Setting out → Steel mold assembly → Internal surface cleaning → Brush isolation agent (release agent) → Inspection and acceptance

②Construction points.

a. Place the steel form on a firmly set and level ground keel, and set out the steel form on the bottom according to the size of the hanging board to ensure it is square;

b. The combined steel formwork is connected with connectors and supported reliably; after the steel formwork is assembled, the local maximum gap between the side formwork, end formwork and bottom formwork working surface shall not be greater than 0.5mm; there should be no displacement when using a gantry crane to test the steel formwork;

c. Use a wire brush to remove dirt from the inner surface of the steel mold, and wipe it clean with a rag to ensure that the surface has no obvious rust stains and is flat and smooth; the inner surface should be a single piece of steel mold, and no joints or welds are allowed; there should be no defects such as cracks, scars, delaminations, etc. If there are some scratches, scratches, indentations and burns, the depth should not be greater than 0.5mm and the width should not be greater than 1mm;

d. Apply the isolation agent (release agent) evenly on the working surfaces of the side mold, end mold and bottom mold; there should be no water marks on the surface of the steel mold before painting;

e. The main content of the inspection is to inspect the geometric dimensions of the inner surface of the combined formwork.


Related news

  • Menu

综合管廊成套装备生产厂家

Links:
Copyright © Jiangsu Zhongyi Building Materials Machinery Co., Ltd All rights reserved record number:Su ICP No. 18031077-1 Mainly engaged in, Welcome to inquire!
Article | Site map | RSS | XML Technical Support: Yicheng Network Disclaimers
#

x